title: Predictive adaptive spectrum
|
|
draft: true
|
|
sr-due: 2022-04-18
|
|
sr-interval: 27
|
|
sr-ease: 252
|
|
---
|
|
|
|
## Review Questions
|
|
1. what is a predictive swd methodology
|
|
1. one that is not flexible, rigid, not incremental, has well defined requirements and is planned in advance
|
|
2. low techincal risk
|
|
|
|
2. what is an adaptive swd methodology
|
|
1. not planned in advance, more flexible, incremental
|
|
2. high technical risk
|
|
|
|
3. what is meant by the waterfall and the modified water fall methodology
|
|
1. waterfall methodology is when there are a set of steps for the development life cycle and each one "flows" into the next with no returnig to previous steps
|
|
|
|
4. Within an adaptive methodology, what are:
|
|
1. iterations
|
|
- one cycle of the steps
|
|
1. incremental development
|
|
- when projects are completed in a series of interations
|
|
2. walking skeleton
|
|
- when development begins by creating a bare bones (similar to mvp) structure
|
|
|
|
___
|
|
|
|
tags: #review
|
|
# Predictive adaptive spectrum
|
|
|
|
## Predictive
|
|
- panned project in advance
|
|
- requirements well defined
|
|
- low technical risk
|
|
|
|
#### waterfall
|
|
- "water fall" -assumes phases are completed sequentially (no overlap or iteration)
|
|

|
|
- modified water fall - slightly less rigid verision of "waterfall" which allows some overlap
|
|

|
|
|
|
|
|
## Adaptive
|
|
- more flexible, changes as you go. cannot be planned in advance
|
|
- requirements uncertain
|
|
- high techinal risk
|
|
|
|
e.g.,
|
|

|
|
|
|
#### Iterations
|
|
"micro projects"
|
|
|
|
#### Incremental development
|
|
complete projects in small iterations
|
|
"growing" a system
|
|
|
|
#### Walking skeleton
|
|
complete structure is built with bare bones functionality
|
|
further functionality added iteratively
|
|
similar to minimum viable product (MVP) |